Burlington Announces Road Work Improvement Projects

See which road projects are scheduled for this season.

The Town of Burlington announced upcoming road work projects meant to improve traffic on Middlesex Turnpike and South Avenue/Second Avenue. 

According to an announcement on the town web site, the  Middlesex Turnpike – Route 3 Transportation Improvement Project is the Town of Burlington’s continued effort to provide a 21st century transportation system sufficient to support continued economic development and expansion along the Middlesex Turnpike/Route 3 corridor.

"Recognizing that the Town and the State have made prior infrastructure investments to support growth along corridor including Network Drive, 3rd Avenue, and the Avenue, it is imperative to continue that work to the south," the announcement states. 

The projects are spearheaded by the Gutierrez Company and funded through a Mass works Infrastructure Program the following Transportation Improvement. 

The projects that will be undertaken this season are: 

  • Middlesex Turnpike 

The improvements along the Middlesex Turnpike consist of widening Middlesex Turnpike at the Route 128 Northbound Off-ramps to provide a new third northbound through lane and a new exclusive left turn lane.  

The northbound Route 128 off-ramps will be reconstructed to improve the alignment and travel to and from Wheeler Road (West) and the southbound left turn lane on Middlesex Turnpike will be extended increasing storage capacity.  

Find out what's happening in Burlingtonwith free, real-time updates from Patch.

The traffic signal at this location will be adjusted to take advantage of the additional capacity and to improve safety. 

  • South Avenue & Second Avenue

The improvements along South Avenue & Second Avenue consist of widening South Avenue and removing the one-way traffic restriction to improve traffic flow.  

Find out what's happening in Burlingtonwith free, real-time updates from Patch.

A multi-use path will be provided along the westerly side of South Avenue and will connect to the Northwest Park development project.  Second Avenue will be widened to accommodate additional turn lanes at its intersection with Middlesex Turnpike and Burlington Mall Road.  T

he Second Avenue approach to the Middlesex Turnpike will also be modified to better align the eastbound through movement.  The Second Avenue right-turn movement will be designed to provide a protected, canalized approach to the Middlesex Turnpike.